(This page printed from UtahRails.net, Copyright 2000-2011 Don Strack)

To Move A Mountain

Railroads and Mining in Utah's Bingham Canyon

This page last updated on January 25, 2012.

(Return to Bingham index page)

Copper Era, From 1981 to 1989 (Sohio)

(click here for a brief summary history of Sohio and British Petroleum/BP America)

June 4, 1981
Standard Oil Company of Ohio (SOHIO) bought Kennecott Minerals Company (KMC); British Petroleum (BP) owns 53 percent of SOHIO; British government owns 25 percent of BP, Bank of England owns 20 percent. (Salt Lake Tribune, September 24, 1981)

October 1981
Modernization of ore haulage and pit crusher planned, along with a new concentrator site. New smelter began operations in spring 1978. (Salt Lake Tribune, October 30, 1981)

December 1981
Visitor Center at Bingham Mine closed, to be replaced by a new one, to be built later. Bingham Mine has been listed as a National Historic Site since 1972. (Salt Lake Tribune, May 27, 1981)

1981
Production for the Bingham Mine, at 223,123 tons of copper, is 60 percent of all Kennecott Copper's 1981 production of 372,213 tons of copper. (Salt Lake Tribune, April 6, 1982)

March 3, 1982
Kennecott Corporation announced a lay off of 530 employees, about 10 percent of the workforce in Utah, beginning on Sunday March 7, 1982. Copper prices had hit a new low of 70 cents per pound, compared to an average price of 80 to 90 cents per pound. (New York Times, March 3, 1982)

July 1, 1982
910 employees laid off. Lay-offs began on February 12, 1982, with a total so far of 2,000 employees laid off. (Deseret News, July 1, 1982)

Fall 1982
Truck haulage replaced rail haulage between the 5440 level and the 5190 level. (source not recorded)

December 1982
Four 1500 hp locomotives arrive (numbers 714-717), for service as switchers, to replace retired electrics. (source not recorded)

1982
Due to a glut in the copper market, Kennecott has had a $48 million loss during this first quarter. Kennecott began 1982 with 7,300 workers. Ray Mines Division was shut down on May 2, 1982, and mine activity was cut back to care and maintenance on August 15, 1982. (Salt Lake Tribune, July 1, 1982)

September 1982
Copper selling in range of 55 cents per pound in recent months, compared to $1.80 per pound in February 1980. (Deseret News, September 1982)

1983
Kennecott Minerals Company became Kennecott, (an operating company of SOHIO) (source not recorded)

In 1983, the entire mine was converted to shovel and truck mining. Rail haulage was used for reload only, at the 6040, 5840, and 5490-Tunnel levels. The last rail and shovel mining took place between the 5540 and 5990 levels. Prior to the end of 1983 there were 42 truck haulage levels, 36 above the 5990-Level and six below the 5490-Level. The 11 rail haulage levels were between the 5490-Level and the 6040-Level. By this time there was very little ore left above the 6040-Level and all operations were concerned with removal of waste to allow ore mining in the lower levels. (Strack, 1983 research notes)

1983
Kennecott closed its 175 megawatt coal-fired generating station because of financial losses. In the meantime, Kennecott could purchase power from Utah Power and Light at a reduced rate. The generating station's 100 employees remained working for maintenance purposes. (Coal Age, Volume, number 6, June 1983, page 33, "Coal in Brief, Plant Closed") (click here for more information about the Central Power Station)

During 1983 Kennecott was reported as being the nation's largest producer of copper, including production from all four mines: Bingham (Utah), Ray (Arizona), Chino (New Mexico), and Ely (Nevada). (part from New York Times, November 14, 1987, "four years ago")

August 1983
Kennecott's $400 million modernization program depended on proposed property tax breaks by Utah State Legislature. (Deseret News, August 30, 1983)

The last waste train was operated on September 19, 1983. (Strack, 1983 research notes)

September 19, 1983
Switcher number 704 was transferred to Ore Haulage. Renumbered to 123 on 13 January 1984. (from Kennecott records at Dry Fork shops and at Magna engine house)

November 1983
Two pit high cab diesel locomotives (number 784 and 786) were transferred to Ore Haulage (as number 910 and 911) (Strack, 1983 research notes)

July 1, 1984
Kennecott laid off 1,795 workers on July 1, 1984. (Deseret News, July 13, 1984); 2,000 workers (two-thirds of workforce) were laid off. (Deseret News, March 26, 1985)

July 1, 1984
Ore Haulage Department was shut down and the organization was dissolved. Ore trains were to be operated by the mine crews. (Ore Haulage logbook)

September 4, 1984
Former Ore Haulage crews transferred to the mine began the operation of ore trains to Bonneville crusher, using mine locomotives. Trains were moving 35,000 tons per day, using 400 ore cars. (Strack, 1984 research notes)

October 1984
Copper production at Bingham took about 1,200 to 1,400 cars of copper ore to produce about 20 cars of concentrate for the smelter. Kennecott's Chino operation was sending about 10 cars of concentrate per day to the Utah smelter. (Strack, 1984 research notes)

January 1985
Utah legislature exempted Kennecott from paying sales tax on purchases of machinery to replace old equipment and equipment needed to expand operations. (Deseret News, March 26, 1985)

January 6, 1985
Kennecott laid off 100 more workers, leaving just 2,200 workers remaining of a peak in 1980 of 7,300. (Salt Lake Tribune, January 1, 1985)

March 26, 1985
Kennecott announced that it would spend $400 million to modernize its Utah operations. In December 1984, the company had received approval for the zoning changes needed to build the Copperton mill. Contracts with 14 unions were set to expire on June 30, 1986. It was reported that in 1981, Kennecott had 7,400 employees, with an annual payroll of $250 million. "Some 2,500 kennecott workers lost their jobs by the time the shutdown was complete in September [1985]." To fund the Utah modernization program, Kennecott's parent company Standard Oil Company of Ohio, reported that it would take $1.15 billion charge against fourth quarter 1984 earnings, while still reporting a $290 million profit on $3.2 billion in revenues. The $400 million cost of the program was to be spread over a period of three years. (Deseret News, December 3, 1985, citing information in three separate articles)

April 30, 1985
Bingham Canyon Mine operations were shut down. (source not recorded)

August 1985
Magna, Arthur, and Bonneville Mill operations were shut down.

Magna Mill

The Magna Mill was one of the two original mills built in the area by the two Bingham Canyon copper companies. After experimentation with a prototype mill in Copperton, Utah Copper Company built their Magna Mill on a hillside above the Great Salt Lake. The mill opened in 1907 and had reached a capacity of 6000 tons per day by 1908, expanding again in 1911 to 10,000 tons per day. The grinding at the mill was done with 7 foot Chilean mills. After a brief closure between 1919 and 1922, the Magna mill reopened and a froth flotation circuit was added. (Froth flotation experiments were begun in the 1914 and by 1926, the gravity technology had been completely replaced by the flotation method.) At the Magna Mill, sodium xanthate was used as the flotation agent and a plant was added to manufacture the xanthate. But the neutralized reco cresylic acid reagent in use at the adjacent Arthur Mill proved more cost effective and the Magna Mill began using the same reagent in 1933. The Magna Mill remained open during most of the Depression but operated at only a fifth of its capacity. The portions of the plant not in operation were reconditioned at this time. Full scale operations resumed and the normal capacity of the mill was about 40,000 tons/day. When the Bonneville Crusher was opened in 1966, the grinding portion of the Magna mill was no longer needed and it was eventually demolished in 1991-1992. However, the Bonneville Crusher continued to feed the flotation circuits of the Magna Mill and this portion was upgraded in 1975. The concentrates were loaded into rail cars and were shipped to the smelter. The tailings were sent via a flume to the Magna Tailings Pond. The Magna Mill, known also as the North Concentrator, was shut down in 2001.

Arthur Mill

The Arthur Mill was closed in 1985.

In 1906, the Boston Consolidated Company began construction of a large ore milling facility adjacent to the site of the ASARCO smelter. Located on a 810 acre site, the mill was put into operation in 1909 with a capacity of 3000 tons per day. Utah Copper, which was operating its own plant next door, bought out the Boston Consolidated Company and all its facilities in 1910, and Utah Copper ended up with two mills side by side. The former Boston Consolidated Mill, renamed the Arthur Mill, expanded in capacity to 8000 tons per day. Based on the results of flotation experiments which began in 1914, the Arthur mill was equipped with a flotation circuit by 1918 and flotation completely replaced the gravity separation technology by 1926. Flotation reagents tested at the mill included coal tar creosote, petroleum, petroleum residuum, petroleum stove oil, pine oil, reco pine oil, reco turpentine, calura (lime, sulfur and sodium hydroxide), rosin, lime, soap solution, sodium sulphide, sodium hydroxide, light oil, coal tar, phenols, sulphuric acid, alpha naphthylamine, xylidine, thiocarbanilid, ortho toluidine, and potassium ethyl xanthate. In 1924, a typical charge consisted of creosote oil, steam distilled pine oil, sodium hydroxide and sulphur. New reagents for flotation were introduced in 1925 including reco cresylic acid (a reaction product of cresylic acid and phosphorus pentasulfide) and reco alcohol (a reaction product of alcohol and phosphorus pentasulfide). The tailings and whatever reagents were used in the process were discharged to the Magna Tailings Pond.

During the Depression, the Arthur Mill was closed between 1930 and 1936 and the mill was reconditioned at that time. The Arthur Mill then operated until 1966 when the Bonneville Crusher opened. Some ancillary activities continued until 1985. The buildings were demolished in 1988-1989. Only the Arthur Mill Administration Building and a few storage sheds remain of the original mill and its support buildings.

The Arthur mill was shut down in 1984, and was demolished in 1991. The adjacent Magna mill was shut down in 2001 and was demolished in 2007. (Salt Lake Tribune, May 10, 2007)

Bonneville Mill

In 1966, Kennecott opened the Bonneville Crusher, constructed to provide a finer grind for the ore than could be accomplished at the Arthur or Magna mills. When it was first opened, the crusher fed the flotation circuits for both the Arthur and Magna mills. Processing capacity was markedly increased from 90,000 tons per day before the opening of the crusher to 108,000 tons per day shortly after the Bonneville Crusher came on line. Since 1985, the Bonneville Crusher fed only the Magna Concentrator. The Bonneville Crusher was a rod mill which is more effective with harder ores than the facility in Copperton. These harder ores were shipped to the Bonneville Crusher from the pit via rail. After crushing, the ore slurry was sent to the Magna Concentrator for flotation. The Bonneville Crusher and the Magna Concentrator (known as the North Concentrator Complex) were closed in 2001.

February 1986
Actual construction and site preparation started on new $400 million modernization program. (Deseret News, August 2, 1988)

February 27, 1986
Standard Oil of Ohio changed its name to Standard Oil Company on Thursday, February 27, 1986. At the same time, British Petroleum, which owned 55.5 per cent of Standard Oil, doubled it representation of the 14-member Sohio board of directors, from three positions to six positions, and removed both the chairman and the president of Sohio, who had both held those same positions when Sohio took control of Kennecott in June 1981. The acquisition of Kennecott by Sohio had been the subject of shareholder criticism since that time. It was reported that Sohio earnings for 1985 were 79 per cent less than 1984, $308 million compared to $1.49 billion. (Deseret News, February 28, 1986)

September 1986
Bingham Canyon Mine resumed operations.

December 1986
Kennecott reopened the Bonneville crusher and Magna concentrator mill. (Deseret News, January 3, 1989)

March 26, 1987
British Petroleum made its planned offer to buy the remaining 45 percent of Sohio it did not already own. (Toronto Star, March 26, 1987, "today") British Petroleum bought 45 per cent of Sohio, at a reported price of $7.8 billion. (New York Times, September 8, 1989)

May 1987
By mid May 1987, BP owned 95 percent of Standard Oil Company, the new name of the Standard Oil Company of Ohio (Sohio). (New York Times, May 14, 1987)

June 30, 1987
British Petroleum completed its purchase of Standard Oil Company, formerly Standard Oil Company of Ohio. The acquisition was made through BP's wholly owned subsidiary, BP America Inc. (New York Times, June 30, 1987, citing a Reuters story)

July 1987
Smelter produced its first cathode of Utah copper, after reopening of mine.

September 24, 1987
BP America announced the formation of BP Minerals America. The new unit combined the assets of Kennecott Corporation, headquartered in Salt Lake City, and Denver-based Amselco Minerals. BP Minerals America was to be headquartered in Salt Lake City. (BP America news release, dated September 24, 1987, "today")

November 1987
"The nation's largest copper producer four years ago, Kennecott, a unit of the British Petroleum Company, now ranks fourth. It has sold most of one of its three mines to Phelps Dodge and all of another to Asarco Inc and now owns a single mine - the Bingham Canyon mine in Utah, which recently reopened for production." (New York Times, November 14, 1987)

1988
British Petroleum, parent company of BP Minerals America (owner of Bingham Mine), is 21.68 percent owned by the government of Kuwait. They bought the interest after the October 1987 world wide stock market crash, at the urging of the British government. The British had just offered the stock of BP to the open market and the crash was causing it to lose value. (Wall Street Journal, August 10, 1988)

January 1988
The new conveyor belt installed in the 5490 rail tunnel was put into operation in January 1988. The conveyor system consisted of six separate conveyor belts, with the longest, known as C-6, being 17,300 feet in length. By the time it was replaced due to normal wear and tear, in August 2002, the conveyors had carried 700 million tons of 10-inch minus material, from the in-pit crusher, out to the material storage pile adjacent to the Copperton mill. The conveyor belts were 72-inches wide. The C-6 belt was replaced during a normal 10-day downtime to move the in-pit crusher. "After almost 14 years of service, the most critical belt was removed after exceeding all warranty expectations. In particular, it exceeded warranty life by 40 percent and warranty tonnage by 245 percent. The belt was finally replaced [in August 2002] due to the convenience of system downtime created by a crusher move and because of the awareness of the increasing incidence of cord damage/breaks." (Dr. Robin B. Steven, The Goodyear Tire & Rubber Company, "Replacing C-6 Conveyor Belt at Kennecott Copper, Bingham Canyon Copper Mine", http://www.saimh.co.za/beltcon/beltcon12/paper1209.htm)

February-October 1988
"In February [1988], ore was fed to the crusher. By the end of March, the three grinding lines were operating and the flotation circuit was producing copper concentrate. In July, the design through-put rate of 77,000 tons per day was reached. October saw the achievement of targeted metal recoveries that corresponded to the fully modernized operation." (Society of Mining Engineers, "BP Minerals Completes $400 Million Modernization At Bingham Canyon," 1988)

September 1988
Kennecott completed the modernization of its ore processing operations, from mine to mill, to smelter. BP Minerals officials announced the $400 million modernization project in December 1985 as a means of remaining competitive in the world copper market. Actual construction and site preparation began in February 1986. (Deseret News, August 2, 1988)

An open house of the newly completed modernization was held for the media on September 22-23, 1988, in which a six-inch ribbon of copper was cut in a formal ceremony. Before the modernization, rail cars were used to move ore from the mine to the Magna and Arthur mills, a trip of 16 miles over Kennecott's own, private railroad. At the mills, the ore (at about 0.6 to 0.75 percent copper) was crushed and ground, then processed to become copper concentrate (at about 26 percent copper). The concentrate was then shipped from the mills to the smelter, also by rail car. Both mills were closed in 1985, at the same time that mining operations were suspended at the Bingham mine. The modernization program included a new concentrator adjacent to the new Copperton crushing and grinding mill, along with a new primary crusher in the mine, which was then connected to the new secondary crushing and grinding mill built at Copperton. From there, water was added to the finely ground concentrate, and the slurry mix sent by way of a pipeline directly to the smelter. Ore is dumped into a primary crusher in bottom of pit, passed out of the pit by way of an new conveyor belt running through the old 5490 railroad tunnel, to the new Copperton crusher, crushed to a fine powder, added to water and sent via a new six-inch, 17-mile pipeline to the Garfield smelter. (Deseret News, September 23, 1988)

June 1989
World-wide mineral interests of British Petroleum (including the Kennecott Utah Copper unit of BP Minerals America) were sold to RTZ Corporation for $4.4 billion. The name of BP Minerals America, Kennecott Utah Copper was changed to Kennecott Corporation on or about July 5, 1989. (Salt Lake Tribune, July 6, 1989)

***

Creative Commons License Valid XHTML 1.0 Strict Valid CSS!