UtahRails.net

(This page printed from UtahRails.net, Copyright 2000-2017 Don Strack)

Bingham Railroad Tunnels

Index For This Page

This page was last updated on December 1, 2017.

(Return to Bingham Canyon page)

Copper Belt Tunnel

Completed in November 1907 as part of Rio Grande Western's Copper Belt spur to the Boston Consolidated's steel ore bin in lower Carr Fork. This tunnel was built through the ridge that separated Carr Fork from Bingham canyon. This line to the steel ore bins later became Utah Copper's main 'A' level Auxiliary Yard

Bingham & Garfield Tunnels

"The total length of tunneling on the line 4795 ft., in four tunnels of the following lengths: 682, 754, 2079, 1280 ft. There are three steel bridges on the upper end of the line, one across Carr Fork, adjacent to the main delivery yards of the Utah Copper Co., having a length of 690 ft., and a maximum height of 190 ft. The bridge across Markham Gulch is 640 ft. long and 220 ft. high, and the Dry Fork bridge, about three miles from the upper end of the line, is 670 ft. long and 185 ft. high." (Mining & Scientific Press, Volume 103, July 1, 1911, page 18)

There were four railroad tunnels on the Bingham & Garfield Railway in Bingham Canyon. From south to north, they were:

B&G Tunnel No. 1

B&G Tunnel No. 2

B&G Tunnel No. 3

February 15, 1942
Utah Copper locomotive 105 had a boiler explosion that killed both the engineer, Joseph Poulsen, and the fireman, Rhys Thomas. The brakeman, Edward Anderson suffered minor burns because of his location in the brakeman's shanty atop the locomotive tender. The explosion took place at 8:05 a.m. on Saturday February 15, 1942 while the locomotive was inside Tunnel No. 3 on the former Bingham & Garfield line in Bingham Canyon. The locomotive was at the head of a train of 52 empty ore cars returning to the Bingham copper mine from the mill at Magna. (Salt Lake Telegram, February 21, 1942) The usual operating practice was for the locomotive to travel tender first when returning to the mine, putting the brakeman ahead of the locomotive when the explosion took place.

B&G Tunnel No. 4

(Read more about Bingham & Garfield Railway)

'D' Dump Line Tunnels

The 'D' Dump Line extended down-canyon from Carr Fork, eastward along the north side of Bingham canyon, above the Bingham & Garfield mainline. The line had very sharp curves, and three tunnels.

Beyond Tunnel No. 3, the 'D' Dump line extended into the upper parts of Dry Fork, and along with the retired portion of the B&G mainline after 1944 (known as the 'A' Dump line), was used to fill Dry Fork Gulch.

Cross-Canyon Connection

June 1943
The cross-canyon connection was completed at the site of the old Yampa Smelter, providing a railroad connection between the planned 6040-Tunnel and the new Ore Haulage Central Yard, near Dry Fork. The new cross-canyon fill included two short tunnels for the highway and the Denver & Rio Grande Western line. (Kennecott Historical Index)

Kennecott Railroad Tunnels

1955
Eighty percent of all ore mined was moved through the 6040 and 5840-Tunnels. (Kennecott Historical Index)

1958
Seventy five percent of all ore mined came from below the 6340-Level. Seventeen percent of ore mined moves through the 6040-Tunnel with forty percent moving through the 5840-Tunnel. (Kennecott Historical Index)

In 1983, the entire mine was converted to shovel and truck mining. Rail haulage was used for reload only, at the 6040, 5840, and 5490-Tunnel levels. The last rail and shovel mining took place between the 5540 and 5990 levels. Prior to the end of 1983 there were 42 truck haulage levels, 36 above the 5990-Level and six below the 5490-Level. The 11 rail haulage levels were between the 5490-Level and the 6040-Level. By this time there was very little ore left above the 6040-Level and all operations were concerned with removal of waste to allow ore mining in the lower levels.

September 1982 - Truck haulage replaced rail haulage below the 5490 tunnel (rail haulage was replaced above the 5840 tunnel in 1963), leaving rail haulage in place between 5490 and 5840 tunnels.

May 1983 - Power plant at Magna was shut down.

Summer 1983 - Rail haulage was severely curtailed.

September 1983 - Last waste train operated between the 5840 and 5490 tunnels.

Late 1983 - Diesel-powered rail haulage was in place only for reload operations at 6040, 5840, and 5490-Tunnel levels.

6040 Tunnel

January 10, 1944
6040 Tunnel -- Utah Construction Company began work on the tunnel, 4,600 feet long, that was to connect the bottom of the open pit mine with Bingham. Completion was anticipated to be in one year. (Bingham Bulletin, August 4, 1944; December 22, 1944)

June 1944
A Utah Copper photograph dated June 23, 1944 (UCM 288, 6-23-44) shows the lower portal of the 6040 tunnel not yet completed, with wooden concrete forms still on the portal, and no railroad rails in the vicinity.

December 22, 1944
6040 Tunnel -- There remained just 800 feet yet to drive to complete the new railroad tunnel. The new tunnel was 18 feet wide and 22 feet high. The general superintendent of Utah Construction Co. stated that the tunnel would be complete in approximately two months, at a cost of $1,222,000. "Obstacles which have plagued construction crews include two cave ins, one in June, which halted progress for six weeks, and another, which slowed down the crew for two weeks, in July. The shortage of labor has kept shift crews, which in ordinary times number 16 or 18 men, down to 8 and 10. To keep the men needed on the job it has benn necessary to raise the wages of $10 a day, standard tunnel pay all over the country, to $11.70." "Much loose ground has been encountered, necessitating placement of arched supports close to the face and nearer each other than ordinarily required. Until recently the rock excavated from the tunnel has been of little value. The quartzite vein they are now encountering has better grade mineral content." (Bingham Bulletin, December 22, 1944)

January 22, 1945
6040 Tunnel -- "In addition to the increase in [mine] track lengths, 3,972 feet of tunnel was driven on the 6040 Level connection to the pit." (Utah Copper Chronology History, General Manager's Report for 1944, January 22, 1945)

July 7, 1945
6040 Tunnel -- A dinner was held at the Utah Construction company boarding house at Bingham, celebrating the completion of concrete work on the new railroad tunnel, 4,700 feet in length. (Bingham Bulletin, July 13, 1945)

February 4, 1946
6040 Tunnel -- "At the end of the year [1945] the transportation tunnel from the present floor of Utah Copper company's open pit mine was described as 'nearing completion.' It will provide an outlet for sub-level ore." (Ogden Standard Examiner, February 4, 1946)

(This indicates that although the tunnel itself was completed in July 1945, Utah Copper still had extensive work to complete before track could be laid connecting the new tunnel with the lowest track levels in the mine, including considerable excavation, as well as connecting with the new cross-canyon connection. The new connections included new switchback tracks connecting with the waste dump lines higher in the canyon. Other connections included tracks to the new Copperton yard of the new electrified line being built.)

5840 Tunnel

April 9, 1951
The new 5840 tunnel was being driven from a point 50 feet below the current bottom of the open pit mine, and was to be 1-1/3 mile in length. It was to be a standard railroad tunnel, 21 feet wide and 25 feet tall. (Salt Lake Tribune, April 9, 1951)August 1952
The 5840-Tunnel in completed and placed in service. The tunnel was 7,000 feet long. Tracklaying in the tunnel began in January and was completed in March. (Kennecott Historical Index)

August 30, 1952
Drilling came to an end on the new 5840 tunnel on "Saturday" (August 30). The tunnel was 7,042 feet in length. (Salt Lake Tribune, August 31, 1952)

March 26, 1953
First ore trains operated through the new 5840-Tunnel. (Kennecott Historical Index)

(A Kennecott company photo dated March 3, 1953 shows an ore train apparently exiting from the newly completed 5840 tunnel, a short distance from the south side of the C-C cross-canyon connection to Central Yard. Another ore train is shown moving down hill from the 6040 tunnel to the same connection with the cross-canyon connection to Central Yard. The downhill portal of the 5840 tunnel was lower and about 1/4 mile down-canyon from the downhill portal of the 6040 tunnel.)

January 17, 1957
First waste train used 5840-Tunnel. (Kennescope, February 1957)

August 1958
Kennecott began operating waste rock trains through the 5840 tunnel. Previously only ore trains were allowed through the tunnel. The change was because of the expansion of the pit, and more waste was being removed from the lower levels. (Bingham Bulletin, August 8, 1958)

March 2000
The reload facility in the mine was moved to a site below Dry Forks shops. The previous reload site was inside the pit, accessed via rail through the 5840 tunnel, and had been found to be located on top of a pocket of high grade ore. Moving the reload site outside of the mine also allowed the 5840 tunnel to be closed. The rail in the 5490 tunnel had been replaced in January 1988 by a new conveyor belt that moved ore from the primary crusher in the pit, out to the new Copperton concentrator.

March 19, 2000
The last ore train was operated from the last reload site inside the mine, through the 5840 tunnel, down the remaining rail corridor in old Bingham Canyon to Copperton yard. After that date, all ore was loaded at the new Dry Fork reload site, outside of the mine. (Louie Cononelos, email dated December 27, 2011)

5490 Tunnel

November 1956
Actual drilling began on the new 5490 tunnel. (Bingham Bulletin, July 19, 1957)

The new tunnel was to be 18,000 feet long, measure 18 feet wide and 24 feet tall, with a reported cost of $12 million. Two other tunnels were already in place: the 6040 tunnel, completed in 1945, and the 5840 tunnel, completed in 1953. All tunnels were built to reduce mining costs by elimination of the uphaul of ore trains coming from the deepening bottom of the open pit mine. (Ogden Standard-Examiner, February 24, 1957)

1958
During the year, Utah Construction Company made 8,875 feet of progress on the new 5490-Tunnel. (Kennecott Historical Index)

December 19, 1958
The new 5490 tunnel was 92 percent complete. The tunnel was projected to be 18,000 feet in length and to cost $11 million, and would eliminate costly up-hill ore and waste haulage from the bottom of the deepening Bingham open pit mine. (Bingham Bulletin, December 19, 1958)

February 1959
The new 5490-Tunnel was completed at a cost of $12 Million. The tunnel is 18,000 feet long. (Arrington: Richest Hole, page 72)

March 6, 1959
Kennecott announced that the new 18,000-foot tunnel at the 5490-level had been completed. Work had started on October 30, 1956. (Salt Lake Tribune, March 7, 1959)

November 21, 1960
The new 5490 tunnel was completed in March 1959 to a point 150 feet lower than the current bottom level of the open pit mine. In June 1960, Morrison Knudsen began construction of a spiral cut to take railroad tracks down to the new tunnel's Bingham portal. Kennecott was installing permanent railroad track inside the newly completed tunnel. The spiral cut was to be 3600 feet long, at a finished grade of 4 percent. Because the spiral cut was in the actual ore body, the MK earth movers, at 20 cubic yards and 40 tons with each load, were moving the ore to a stockpile on the east side of the mine's bottom level, at a rate of 18,000 yards per day. Kennecott shovels were then loading the ore into trains, with the operation furnishing about one third of the mine's daily production. (Deseret News, November 21, 1960)

May 7, 1961
First ore train used the new 5490-Tunnel, seven weeks after "breakthrough" of the tunnel into the pit. The train was loaded with ore that had been stockpiled from the excavation in the pit for the tunnel portal. (Kennescope magazine, June 1961, page 26; with small photo of empty ore train being pulled by locomotive 869 exiting tunnel)

May 27, 1961
The first train of ore from other levels in the pit moves through the new 5490-Tunnel to Copperton. The track had been connected (using a spiral excavation) with the track of the 5640-Level on May 21st, and electrified on May 25th. (Kennescope magazine, June 1961, page 26)

March 26, 1985
A five-mile conveyor belt system t move the crushed ore to the site of a new grinding and floatation plant one mile north of Copperton. The 72-inch main ore conveyor exited the mine through an existing railroad tunnel at the 5,490-foot level. The conveyor belt would have a capacity of moving 10,000 tons every hour. Along the 5.1 miles of total length, there were five transfer stations, large steel structures several stories high that were needed each time the conveyor belt changed direction. After exiting the former railroad tunnel, the conveyor continued for two miles to the new grinding and floatation complex.

January 1988
The new conveyor belt installed in the 5490 rail tunnel was put into operation in January 1988. The conveyor system consisted of six separate conveyor belts, with the longest, known as C-6, being 17,300 feet in length. By the time it was replaced due to normal wear and tear, in August 2002, the conveyors had carried 700 million tons of 10-inch minus material, from the in-pit crusher, out to the material storage pile adjacent to the Copperton mill. The conveyor belts were 72-inches wide. The C-6 belt was replaced during a normal 10-day downtime to move the in-pit crusher. "After almost 14 years of service, the most critical belt was removed after exceeding all warranty expectations. In particular, it exceeded warranty life by 40 percent and warranty tonnage by 245 percent. The belt was finally replaced [in August 2002] due to the convenience of system downtime created by a crusher move and because of the awareness of the increasing incidence of cord damage/breaks." (Dr. Robin B. Steven, The Goodyear Tire & Rubber Company, "Replacing C-6 Conveyor Belt at Kennecott Copper, Bingham Canyon Copper Mine")

Bingham-Lark Tunnel

April 15, 1951
The new Bingham-Lark tunnel for United States Smelting, Refining and Mining was "bored through" on Sunday April 15, 1951. The work had started two and a half years before, with Kennecott paying the full cost of $6 million. The length was reported as 21,014 feet, or 3.9 miles. Construction was being completed by Utah Construction company. The tunnel was at the 5600-foot level, and a shaft would be completed to connect the new tunnel with the old Niagara tunnel at the 6688-foot level. Work began in November 1948, and was scheduled for completion in summer 1952. (Deseret News, April 16, 1951)

(See also, information about the Mascotte Tunnel)

Bingham-Copperfield Vehicular Tunnel

Although not a railroad tunnel, many who lived in Bingham Canyon, or who visited there recall the vehicular tunnel that connected Bingham with Copperfield.

February 25, 1937
Utah Copper offered $600,000 for Ohio Copper's property in Bingham Canyon. Utah Copper needed the surface for expansion of its open pit mine, and a portion of the underground workings for the proposed vehicular tunnel between Bingham and Copperfield. The vehicular tunnel would allow Utah Copper to close the county road at the bottom of Bingham Canyon. (Deseret News, February 25, 1937)

February 13, 1938
Contractor crews made a perfect hole-through on the vehicular tunnel between Bingham and Copperfield. (Utah Copper Company Chronology, citing the "Mines Annual Report, 1938")

December 26, 1938
The Bingham-Copperfield vehicular tunnel was completed. (Utah Copper Company Chronology, citing internal company documents)

February 4, 1939
Copperfield vehicular tunnel was opened for traffic. The tunnel, 7,000 feet long, had been completed in December 1938 and was built at a cost of $1.4 Million. The tunnel rose from 6,100 feet elevation at Bingham to 6,600 feet at Copperfield, at a 6.4 percent grade. The old county highway in the bottom of the canyon was closed and the tunnel was deeded to Salt Lake County as its replacement. The tunnel was used by about 850 cars that first day and could accommodate 1,100 cars per day. Utah Copper began immediately to fill across the old county road, connecting the east and west sides of 'C' Level. (Utah Copper Company Chronology, citing the "Mines Annual Report, 1938")

By mid February 1939, Utah Copper started a fill that would connect the east and west sides of C-Level, across the old county highway. Auto traffic was now using the new Copperfield vehicular tunnel. (Kennecott Historical Index)

At the same time, the U. S. District Court granted Utah Copper's request that the new tunnel be disconnected from Bingham City, and turned over to Salt Lake County ownership and maintenance. (Bingham Bulletin, January 20, 1939)

Traffic in the tunnel was one-way, controlled by "electric eye" that in turn controlled electric traffic signals. Flag men communicating by telephone were used regularly when the traffic lights were not working properly.

1941
The second visitor observation point for the public to view the mine was built in 1941 and was located in Copperfield at the upper end of the vehicular tunnel completed in 1939. The observation point was reached by way of the vehicular tunnel from Bingham, which curved into the mountain to avoid the slowly expanding pit operations.

October 8, 1956
The observation point at Copperfield was closed in October 1956. Over 1.5 million visitors had seen the pit from the Copperfield location since it was completed "some 15 years ago." (circa 1941). The Bingham-Copperfield tunnel remained open for local residents. (Bingham Bulletin, October 5, 1956)

April 22, 1960
The Salt Lake County Commission voted on a resolution to turn the Bingham-Copperfield tunnel over to Kennecott as a private road. A survey over a recent 14-hour period showed that the tunnel was used by 300 cars, carrying 1,200 men, of which 1,195 were Kennecott employees, and the remaining five were employees of another mining company. Kennecott had requested that the county complete some needed repairs on the road through the tunnel. (Bingham Bulletin, April 22, 1960)

August 10, 1960
The Bingham-Copperfield tunnel was abandoned by Salt Lake County, and became a private road for exclusive use by Kennecott and its employees and contractors. (Bingham Bulletin, August 12, 1960, as voted on "Wednesday" at the commission meeting.)

###