Utah Transit Authority's FrontRunner Commuter Rail — Status
This page was last updated on September 27, 2006.
Notes:
- Milestone dates are largely estimated based on projected schedules.
- Construction sequence generally proceeds from clearing ("grubbing") existing vegatation, then bulk excavation and pole line removal, then drainage and utility work, then sub-railbed and embankment work, then railbed work, then actual trackwork (including ties and rail). Many tasks overlap throughout the project schedule, depending on subcontractor schedules and issue resolution.
- Trackwork includes subballast, ballast, ties and rail
UTA Area 1 (Salt Lake City to North Salt Lake)
UTA Area 2 (North Salt Lake to Centerville)
UTA Area 3 (Centerville to Sunset)
UTA Area 4 (Sunset to Ogden)
UTA Area 5 (Ogden)
UTA Area 6 (Ogden to Pleasant View)
UP signal upgrades
UP trackage changes
Area 1 (Salt Lake City to North Salt Lake)
Salt Lake City – 800 S to 250 S (Area 1-1)
- (work not started)
Salt Lake City Station (250 S)
- (work not started)
Salt Lake City – 250 S to North Temple, including Grant Tower (Area 1-2)
- (work not started)
North Temple Station (200 N)
- (work not started)
Salt Lake City – North Temple to 600 N (Area 1-3)
- (work not started)
Salt Lake City – 600 N to 1800 N, passing UP North Yard (Area 1-4)
New UP main lines (along west side of North Yard)
- Demolition of Tracks 15 & 16 started 4/10/06
- Demolition of Track 9 started 6/12/06
- New mainline subgrade started 6/5/06; completed 8/7/06
- Trackwork started 8/7/06
- Realign 3100 ft mainline, 4800 ft yard tracks
- Construct 10,000 ft mainline (new Track No. 1 and new Track No. 2)
- Construct 2000 ft yard tracks
UTA main lines (along east side of North Yard)
- (work not started)
Salt Lake City – Warm Springs Maintenance Facility
- (work not started)
Area 2 (North Salt Lake to Centerville)
Salt Lake City – 1800 N to Center Street (North Salt Lake) (Area 2-1)
- 1800 N crossing started 5/30/06; completed 6/11/06
- UP grading started 5/22/06
- UTA main line (work not started) (includes former UP intermodal yard at Becks)
North Salt Lake – Center Street to 1100 N (Woods Cross) (Area 2-2)
- Drainage and utility work started 8/14/06
- Clearing and earthwork started 9/11/06
- Center St. crossing work started 10/16/06
North Salt Lake – 1100 N to 1500 S (Woods Cross) (Area 2-3)
- Clearing and earthwork started 8/28/06
- Connection to UP Pioneer Industry Track No. 1 out of service 9/25/06
- Subgrade and embankment work started 10/2/06
Woods Cross – 1500 S to 500 S (Area 2-4)
- Clearing and earthwork started 8/14/06
- Subgrade and embankment work started 9/13/06
- Trackwork started 10/9/06
- 1500 S crossing work started (9/18/06)
- 500 S crossing work started (9/25/06)
Woods Cross Station (700 S)
- 800 W closed, 6/7/06
- Excavation work and site grading started 6/12/06; completed 7/19/06
- Retaining walls and footings started 7/19/06; completed 9/5/06
Woods Cross – 500 S to Pages Lane (Area 2-5)
- Excavation work started 7/17/06; completed 8/18/06
- Subgrade and embankment work started 8/21/06
- Trackwork started 10/13/06
Centerville – Pages Lane to Parrish Lane (Area 2-6)
- Excavation work started 7/27/06
- Subgrade and embankment work started 8/14/06
- Pages Lane crossing started 8/21/06; completed 9/27/06
- Trackwork started 9/15/06
Area 3 (Centerville to Sunset)
Centerville – Parrish Lane to Glovers Lane (Area 3-1)
- Parrish Lane overcrossing retaining wall changes started in July 2005; completed 4/17/06
- Excavation work started 4/17/06
- Subgrade and embankment work started 4/17/06; completed 8/28/06
- Trackwork started 9/5/06
Farmington – Glovers Lane to Legacy (Area 3-2)
- Excavation started by 4/3/06
- Subgrade and embankment work started by 4/3/06; completed 8/28/06
- Trackwork started 9/5/06
Farmington Station (Park Lane)
- Includes elevator and pedestrian overcrossing for access to parking and Station Park development
- UP track realignment started by 4/10/06; completed 5/2/06
- Retaining walls and footings started 4/10/06
- Station platform decking started
- Trackwork (including station siding) started 8/5/06
Farmington – Legacy to Rest Area (UP Mile Post 800) (Area 3-3)
- Subgrade and embankment work started 4/20/06
- Trackwork started 6/28/06; completed
Kaysville – Rest Area to Burton Lane (Area 3-4)
- Subgrade and embankment work started, 9/05
- Trackwork started 5/10/06; completed
Kaysville – Burton Lane to Old Mill Lane (Grain Elevators) (Area 3-5)
- Includes UTA passing siding
- Subgrade and embankment work started in early July 2005; completed 4/24/06
- Trackwork started 5/3/06; completed 8/4/06 (First UTA rail laid 5/3/06)
Kaysville – Old Mill Lane to Gentile Street (Layton) (Area 3-6)
- Includes grade separation (overcrossing) for 200 N (I-15 exit)
- Layton Feed & Grain building demolished, 5/1 to 5/6/06
Layton Station (500 S)
- Excavation work and site grading started 9/11/06
- Retaining walls and footings started 9/25/06
Layton – Gentile Street to W Hill Field Road (Area 3-7)
- Drainage and utility work started 9/8/06
Layton – W Hill Field Road to 1000 E (Clearfield) (Area 3-8)
- Drainage and utility work started 9/28/06
Clearfield – 1000 E to 700 S (Area 3-9)
- UP signal upgrade started 7/5/06
- Drainage and utility work started 9/5/06
- Excavation work started 8/2/06
- Antelope Drive overcrossing retaining wall started 8/21/06
Clearfield Station (1250 S)
- (work not started)
Clearfield – 700 S to Center St. (Area 3-10)
- Excavation and clearing work started 10/9/06
Clearfield – Center St. to 800 N (Area 3-11)
- UP realignment of main lines started before 4/24/06; cutover on 8/7/06
- Excavation and clearing work started 7/10/06
- Subgrade and embankment work started (?)
Clinton/Sunset– 800 N to 1800 N (Sunset) (Area 3-12)
- Excavation work started before 4/24/06; completed 8/1/06
- Subgrade and embankment work started 8/28/06; completed 9/18/06
- Trackwork started 10/6/06
- 1300 N crossing started 7/15/06; completed 8/14/06
Area 4 (Sunset to Ogden)
Clinton/Sunset – 1800 N to 6000 S (Roy) (Area 4-1)
- Excavation work started before 4/10/06; completed 6/25/06
- Subgrade and embankment work started 4/17/06; completed 9/14/06
- Trackwork started 9/29/06
- 6000 S crossing completed 8/5/06
- 2300 N crossing complete by 4/10/06
- 1800 N crossing started before 4/10/06; completed 5/15/06
Roy – 6000 S to 4800 S (Area 4-2)
- Excavation work completed by 4/10/06
- Subgrade and embankment work started by 4/17/06; completed 8/24/06
- Trackwork started 8/28/06
- 5600 S overcrossing retaining wall changes complete by 5/1/06
Roy – 4800 S to 4000 S (Area 4-3)
- Excavation work completed by 4/10/06
- Subgrade and embankment work started by 4/17/06; completed 8/14/06
- Trackwork started 8/21/06
- 4800 S crossing started 8/21/06; completed 9/16/06
Roy Station (4100 S)
- Platform grading started 5/30/06; completed 6/5/06
- Platform walls and footings started 6/5/06; completed 9/5/06
Roy – 4000 S to 3300 S (Ogden) (Area 4-4)
- Excavation work started before 4/10/06; completed 5/22/06
- Subgrade and embankment work started 6/19/06; completed 7/20/06
- Trackwork started 8/21/06
- 4000 S crossing completed 5/22/06
- 3300 S crossing completed 8/7/06
Ogden – 3300 S to 1100 W (Pennsylvania Ave) (Area 4-5)
- Excavation work started before 4/10/06; completed 8/14/06
- Subgrade and embankment work started 9/5/06
- Trackwork started 10/6/06
- 3300 S crossing started 8/7/06; completed 8/21/06
Area 5 (Ogden)
Ogden – 1100 W to Weber River (Area 5-1)
- Excavation work 1100 W to I-15 started 8/14/06
- Excavation work I-15 to Weber River started 4/10/06; completed 7/10/06
- Subgrade and embankment work started 9/18/06
- West abutment, piers, footings, and girders complete by 4/10/06
- West embankment fill started 4/10/06
Ogden – Weber River to South Crossing (Area 5-2)
- Overcrossing Weber River and UP Bridge Junction
- Bridge spans 1 to 4 installed 4/24/06
- Bridge deck installation started, 4/24/06
- Bridge spans 5-6 installed 7/17/06
Ogden – South Crossing to North Crossing (Ogden Fill) (Area 5-3)
- 1500 feet long by 40 feet high connecting two bridges with 200,000 cubic yards of earth
- Ogden Yard Fill started in July 2005, located atop site of UP's former Ogden roundhouse
- UP realignment of north leg of Ogden wye (known as "New Pork & Beans") complete by 4/24/06, cutover on 6/5/06
- UP mainline realignment completed 8/21/06
Ogden – North Crossing to Wall Ave (Area 5-4)
- Pier construction started 5/12/06
- UP access to Cereal Foods
Ogden Station (2350 S) (Area 5-5)
- (work not started)
Ogden – Wall Ave to 1700 S (Cecil Junction) (Area 5-6)
- (work not started)
Area 6 (Ogden to Pleasant View)
Ogden – 1700 S to 2700 N (Pleasant View) (Area 6-1)
- Joint UP/UTA operation, Cecil Junction to Pleasant View
- (work not started)
Pleasant View Station
- (work not started)
To clear the east side of its right-of-way for use by UTA Frontrunner tracks, Union Pacific needed to relocate several of its lineside signals and signal bungalows, along with the hot box detector at Mile Post 800 near the I-15 rest area between Farmington and Kaysville. To manage the signaling changes, UP split the route into six different "phases", with the following start and end points:
- Phase I - Sunset (800 N) to Ogden
- new overhead signals at 3300 S (Ogden)
- new overhead signals at 4800 S (Roy)
- new overhead signals at C.P. East Clearfield (2000 N, Sunset)
- completed, cutover on (date?)
- Phase II - Ogden
- completed, cutover on (date?)
- Phase III - Farmington to Sunset (800 N)
- includes new hot box detector at MP 800 (Shepard Lane)
- new overhead signals between Glovers Lane overcrossing and State Street overcrossing
- new overhead signals between Park Lane overcrossing and Shepard Lane overcrossing
- new overhead signals at Burton Lane
- projected completion on 9/30/06
- Phase IV - North Salt Lake to Farmington
- new overhead signals at 400 N Bountiful
- new overhead signals at Centerville, just north of Parrish Lane overcrossing
- completed, cutover on 7/17/06
- Phase V - Salt Lake City
- new signals and controls for new main lines along west side of North Yard
- new signals and controls for Grant Tower trackage
- Phase VI - Ogden to Pleasant View
- joint UP/UTA operation and control
To make way along the eastward part of its right-of-way for UTA Frontrunner tracks, Union Pacific has needed to realign several portions its existing trackage, as follows:
- Grant Tower (Salt Lake City)
- reconfigure and realign tracks throughout Grant Tower interchange
- (not started)
- Salt Lake City, 200 N to 1800 N
- reconfigure and realign tracks north of 1800 N, to allow for UTA track along east side
- install two new mainlines 10,000 feet long between 500 N and 1800 N
- realign various yard tracks along west side of North Yard
- reconfigure and realign tracks between 200 N and 500 N, to allow for UTA track along east side
- work started June 2006
- UTA to take over former UP passenger mains along east side from 400 N to 1800 N
- Farmington Station
- realign tracks to make room for UTA tracks and station
- completed 5/2/06
- Clearfield Yard
- reconfigure and realign tracks throughout Clearfield yard to make room for UTA track along east side
- work started May 2006
- Ogden Wye and Yard
- reconfigure and realign tracks from Bridge Junction to old Ogden main yard to make room for UTA overcrossings and fill
- Ogden Wye (north leg and "Pork & Beans") completed by late April 2006
- work started March 2006; completed, cutover on 6/26/06
As of August 2006, there are no plans for any operational connection between UP tracks and UTA tracks, other than some minor access where UP industrial spurs are east of UTA tracks at Cereal Foods (Ogden), Old Mill (Kaysville), and Warm Springs (900 N, Salt Lake City).